Estimate at completion is the number that moves profit

A small change in the estimate at completion moves recognised profit on a large contract materially. The estimate comes from the project manager.

Key Takeaways
  • Percentage of completion accounting derives recognised revenue and profit from the ratio of costs incurred to estimated total costs.
  • The estimate at completion is therefore the single most influential input into a contractor's reported profit.
  • It is usually supplied by project managers, whose performance is assessed on the same number.
  • Profit fade, where estimated margin declines progressively as a job proceeds, is the pattern this incentive produces.
  • Independent challenge based on historical accuracy is the control, and it does not require doubting anyone's integrity.

There is a number in every contractor's monthly reporting that has more effect on reported profit than any other, and it is not produced by the finance function.

The estimated cost at completion determines percentage complete, which determines earned revenue, which determines recognised profit on every active contract.

It is supplied by the people running the jobs, who are measured on the margins those jobs deliver, and it is submitted monthly under time pressure alongside everything else a project manager is responsible for. That is not a criticism of anyone. It is a structural feature that deserves a control, and it has a direct effect on the balances discussed in retention and release timing, since a job whose completion date moves moves its retention release with it.

Percentage of CompletionEstimatesConstructionGovernanceProfit Fade
01

How the estimate reaches profit

Percentage complete is commonly measured as costs incurred divided by estimated total costs. Earned revenue is that percentage applied to the contract value. The arithmetic is simple enough that it rarely gets checked, which is part of why attention concentrates on the calculation rather than on the input that drives it.

So an estimate that is understated raises the percentage complete, raises earned revenue and raises recognised profit in the current period.

The effect reverses later, when actual costs exceed the estimate, which is what produces the pattern of declining margins as a job progresses. Because the reversal lands in a later period, it is often explained as a project problem rather than as an estimating one, which removes the prompt to examine how the original estimate was arrived at.

Because everything on the work in progress schedule derives from this number, the schedule cannot be more reliable than the estimates behind it.

A finance manager working with a laptop and calculator
The estimate determines percentage complete, which determines recognised profit.
02

Four reasons estimates stay optimistic

None of these involves anyone acting improperly, which is why the control has to be structural rather than personal.

Performance measurement: Project managers are assessed on job margin, and the estimate determines the margin reported this month.
Genuine optimism: Recovery plans are usually believed by the people who make them, particularly early in a difficulty.
Unpriced change orders: Work performed on the expectation of approval, where costs are known and the revenue is not yet, distorting the picture as unapproved change orders describes.
Timing of bad news: An estimate revision is a conversation nobody wants to have in the week it becomes apparent.
03

What independent challenge looks like

The useful control is not a finance person disputing a construction estimate on technical grounds, which is rarely productive and rarely welcome.

It is a comparison against history. How accurate were this project manager's estimates on previous jobs at the same stage of completion, and in which direction did they move.

That comparison is evidence based, unemotional and specific. It changes the conversation from a disagreement about judgement to a question about pattern.

It also requires estimate history to be retained rather than overwritten each month, which is a data decision made long before the conversation, in the way retained evidence usually is.


Challenge the pattern, not the person. History is a better argument than opinion.
04

Three signals worth monitoring

Each is derived from data you already have, provided estimate history is kept.

SignalWhat it indicatesThreshold to investigate
Margin fade by jobEstimated margin declining consistently as completion increases.Any consistent direction across several revisions on the same job.
Estimator accuracy by personSystematic optimism or conservatism by individual.A persistent one directional variance across multiple completed jobs.
Cost to complete versus remaining workWhether the estimated remaining cost is plausible given the physical work remaining.Jobs above ninety percent complete with disproportionate cost remaining.

Revenue recognition on long term contracts and the treatment of estimate revisions depend on the applicable framework. Confirm the approach with your auditors.

"

Finance owns the calculation. Someone else supplies the number that drives it.

ChatFin
05

Putting a control around the estimate

Four steps that add rigour without turning the monthly estimate round into an adversarial process.

Retain every estimate version

With the date and the person, so accuracy can be measured retrospectively rather than argued about currently.

Report fade by job monthly

Estimated margin this month against last month, per job, as a standing item rather than an investigation.

Review estimator accuracy annually

Completed jobs against the estimates given at fifty and seventy five percent complete, by individual.

Require support for large revisions

Above a threshold, a written explanation of what changed, which is a normal control rather than a challenge, as in any sign off requirement.

A person working through receipts with a calculator
Historical accuracy is a better basis for challenge than opinion.
06

Two ways firms handle the estimate

The difference is whether the estimate is a submission or a discussion.

Answer

Estimates submitted and accepted

Project managers submit, finance calculates, and the only challenge occurs when a job goes visibly wrong, by which point the reversal is large.

Answer

Estimates reviewed against history

A monthly review comparing revisions and a periodic accuracy assessment, which surfaces drift early and reduces the size of any single correction.

07

How ChatFin supports estimate governance

The value here is in retention and comparison rather than in the estimating itself, which is a construction discipline.

Estimate history retained: Every version with its date and author, so accuracy can be measured over time rather than reconstructed.
Fade reported automatically: Movement in estimated margin by job prepared each period with the drivers identified for review.
Outliers surfaced: Jobs and patterns that diverge from historical behaviour raised as exceptions rather than found in a review, alongside close metrics that change behaviour on the same contracts.

The estimates, the recovery plans and the judgement about what a job will ultimately cost belong to your project leadership.

Free tool

AI Cost Estimator for the CFO Office

Four inputs. A first year range, a timeline, and three delivery models compared. No login required.

Frequently Asked Questions

Is optimistic estimating a control failure?

Not necessarily, and it is a structural risk that deserves a control. Project managers are measured on the margins the estimate produces, and recovery plans are usually genuinely believed. The control is comparison against historical accuracy rather than any assumption about intent.

What is profit fade?

The pattern where estimated margin on a job declines progressively as the job proceeds, usually because early estimates were optimistic and costs are recognised as they emerge. It is visible in monthly comparisons of estimated margin by job, provided estimate history is kept.

How do we challenge an estimate constructively?

With evidence about pattern rather than opinion about judgement. Estimator accuracy on completed jobs, measured at comparable stages of completion, converts a disagreement into a question about history, which is a far easier conversation to have.

Should finance set the estimates?

No. Finance is not positioned to estimate remaining construction costs. What finance can own is the process: retaining versions, reporting movement, measuring accuracy and requiring support for large revisions.

Keep the history

The estimate drives the profit. Measure how good it has been.

Retaining every estimate version, reporting fade monthly and reviewing estimator accuracy annually gives the challenge an evidence base rather than an opinion.

If you want a first year range for estimate tracking and margin fade reporting, the estimator gives one in about a minute. The practical test is whether someone outside the team could reach the same answer from the records you keep, which is usually a stricter standard than the one applied internally.

Open the estimator
Book a Demo
Put it on your own numbers

See what this looks like in your ERP.

We will walk through the workflow behind this article on the system you already run, using your own data, and show what a first phase would actually cover.

✓Runs on the ERP you already have, on the version you already run
✓Every action prepared as a draft that a person approves before it posts
✓A first phase scoped against your real workflows, not a generic package
Schedule a Demo
Confidential & private

This article is general information for finance and accounting teams. It is not legal, tax, accounting or investment advice. Dates and thresholds are given as published at the time of writing and several of these timelines have moved before, so confirm the current position with your advisers and with the relevant authority before acting.

Photos by Karola G and Tima Miroshnichenko, free to use under the Pexels License (commercial use, no attribution required).