Migration projects test whether the new system works. Rather fewer prove that everything from the old one actually arrived, which is the question an auditor asks and the one nobody prepared for.

Key Takeaways
  • Testing proves the new system functions. Reconciliation proves the data arrived. They are different exercises and the second is usually under resourced.
  • Three levels are needed: control totals, record counts, and open item detail. Matching at one level and not the others is a common false comfort.
  • Balances can tie while the detail underneath is wrong. A control account agreeing to the penny says nothing about whether the subledger items behind it are the right ones.
  • Run the reconciliation three times: a dry run before cutover, at cutover, and again after the first close in the new system.
  • Retain the reconciliation as permanent evidence. It will be requested at the next audit and it cannot be recreated once the legacy system is decommissioned.

The migration plan has a testing workstream, a training workstream, and a cutover weekend with an hour by hour schedule. All of that is about whether the new system does what it should.

Underneath it is a quieter question. Did everything in the old system arrive in the new one, unchanged, and can you show that it did.

It gets asked properly for the first time at the audit following go live, by which point the legacy environment may be read only, partially decommissioned, or gone.

ERP MigrationCutoverData MigrationReconciliationGo LiveControl Totals
01

Three levels, because one is not enough

The most common false comfort in a migration is a trial balance that ties. It is necessary, it is reassuring, and it proves considerably less than people assume.

Level one

Control totals

Trial balance by account, in both systems, at the same cut. Catches wholesale omission and gross error, and will not catch anything that nets.

Level two

Record counts

Number of open invoices, customers, vendors, assets, and journals by type. Catches records that arrived merged, duplicated, or filtered out by a rule nobody documented.

Level three

Open item detail

Item by item comparison of the populations that matter: open receivables, open payables, fixed asset records, and inventory. Catches the case where the total is right and the composition is not.

The trap

Ties at level one only

A receivables control account can agree exactly while the underlying invoices are attributed to the wrong customers or carry the wrong due dates. Aging, collections, and cash forecasting all break afterwards.

Dry runfull reconciliationon a copyCutoverfinal extractreconciledDay 1opening balancessigned offFirst closere-reconcilein new systemArchiveretain aspermanent evidence
The dry run is what makes the cutover weekend calm. It is also the first thing cut when the timeline slips.
02

The failures that do not announce themselves

A migration failure that stops the system is discovered immediately and fixed. The dangerous ones are the failures that leave a working system holding subtly wrong data.

Dates defaulted because the source field was empty. Records excluded by a filter written for the dry run and never removed. Currency amounts loaded at a different rate than the source. Rounding applied at a different precision. Open items merged because two records shared a key that was unique in the old system and not in the new one.

Every one of these produces a system that works. They surface weeks later as an aging report that looks wrong, a depreciation charge that does not match the schedule, or a customer disputing a due date.

A person using a calculator at a desk arranged with files and stationery
A trial balance that ties is necessary and proves less than people assume. Photo by Mikhail Nilov via Pexels
Colleagues in a business meeting discussing data and charts at the office
The reconciliation is evidence, and it cannot be recreated once the legacy system is switched off. Photo by Pavel Danilyuk via Pexels

Freeze the source and take a definitive extract

With a timestamp and a hash where possible. Every later comparison refers back to this extract rather than to a system that may still be changing.

Reconcile control totals by account

In both systems, at the same cut, including accounts with nil balances since those are where omissions hide.

Reconcile record counts by type and status

Open, closed, and partially settled separately. A count that matches in total can conceal status changes that break aging.

Reconcile open item detail for the populations that matter

Receivables, payables, fixed assets, and inventory at minimum. Item by item, on key fields including dates and currency.

Investigate and document every difference

Including the ones you accept. An accepted difference with a written reason is evidence. An unexplained one is a finding.

Re-run after the first close in the new system

New system behavior over a full period surfaces issues that a static comparison at cutover cannot.

Archive the whole set before decommissioning

With the extracts. This package is what answers the audit question, and it has a short window in which it can be assembled.

A trial balance that ties is necessary and not sufficient. Balances can agree exactly while the items underneath them are attributed to the wrong counterparties or carry the wrong dates.
"

Testing proves the system works. Reconciliation proves the data arrived. Only one of them gets a workstream.

ChatFin
Where ChatFin fits

Running the three level comparison automatically

ChatFin is an AI platform for the financial close, built for enterprise finance teams and connected directly to the ERP you already run, including Oracle NetSuite, SAP Business One, JD Edwards, Acumatica, Microsoft Dynamics 365, and Sage Intacct.

For cutover, a ChatFin agent runs the three level comparison between the legacy extract and the new ERP: control totals by account including nil balances, record counts by type and status, and item by item comparison of open receivables, payables, assets, and inventory on key fields.

Differences are grouped by likely cause, such as defaulted dates, filtered records, or key collisions, and the full package is assembled as retained evidence while the legacy extract is still available. ChatFin agents read live ERP data rather than a static export, and every action they take is prepared as a draft that a named person reviews and approves before anything posts. The approval record is retained, which is what turns an automated step into evidence rather than a gap in the trail.

Talk to us about this workflow
Colleagues meeting across a table with documents and a clipboard
The reconciliation is evidence with an expiry date attached to the legacy system. Photo by MART PRODUCTION via Pexels

Frequently Asked Questions

What is ERP cutover reconciliation?

It is the set of controls proving that financial data moved from a legacy system to a new one completely and without alteration. It operates at three levels: control totals by account, record counts by transaction type and status, and item by item comparison of open populations such as receivables, payables, and fixed assets.

Is a matching trial balance enough?

No. A trial balance that ties is necessary and proves considerably less than people assume. A control account can agree exactly while the items underneath are attributed to the wrong counterparties or carry defaulted dates, which breaks aging, collections, and depreciation schedules weeks after go live.

What migration errors are hardest to detect?

The ones that leave a working system holding subtly wrong data: dates defaulted where the source was empty, records excluded by a filter left over from a dry run, amounts converted at a different rate or precision, and open items merged because a key that was unique in the old system was not unique in the new one.

When should the reconciliation be performed?

Three times. A full dry run before cutover on a copy of the data, the definitive reconciliation at cutover, and a repeat after the first close in the new system, since a full period of live behavior surfaces issues that a static comparison cannot.

Why archive the reconciliation?

Because it is audit evidence that cannot be recreated once the legacy environment is read only or decommissioned. The window for assembling the package is short, and the request for it usually arrives at the audit following go live.

References and further reading

Prove it while you still can

Archive the package before decommissioning.

The reconciliation is evidence with an expiry date. Once the legacy environment is gone, the question can be asked and no longer answered.

ChatFin can run the three level comparison between the legacy extract and the new ERP and assemble the retained evidence package.

Book a Demo
Close governance, handled

See this running against your own ledger.

We will look at the accounts, the entries, and the evidence trail behind them in your ERP, and show what an agent prepares before a person approves it.

✓Reads your live ERP data, not an export from last quarter
✓Runs on the ERP you already have, on the version you already run
✓Every action prepared as a draft that a person approves before it posts
Schedule a Demo
Confidential & private

Image credits. Photography via Pexels, free to use under the Pexels License (commercial use, no attribution required). Photographers are credited beneath each image as a courtesy. Product visuals and all diagrams © ChatFin; diagrams may be reproduced with attribution and a link to this page.

Disclaimer. This article is general information on accounting and close operations, not accounting, audit, tax, or legal advice. Confirm the treatment of any specific transaction with your own advisors and auditors. Third party product names are the property of their owners and are referenced descriptively only.