A verbal change order is still revenue

The site instruction was given, the crew did the work and the cost is in the job. The paperwork is somewhere in a chain of emails.

Key Takeaways
  • Costs on unapproved change work are recognised as incurred, which distorts percentage complete if the related revenue is not recognised.
  • Whether revenue can be recognised depends on enforceability of the right to payment rather than on the reasonableness of the claim.
  • Unapproved change orders are one of the largest sources of underbillings on a work in progress schedule.
  • The practical control is documentation at the point of instruction rather than reconstruction during a claim.
  • A register of pending change orders with status and value is the artefact that makes this manageable.

Every construction project generates changes. Ground conditions differ from the survey, the client wants something moved, a design detail does not work in practice.

The work happens, because a project cannot stop while paperwork is prepared, and the cost goes into the job immediately. The associated retention is withheld from the eventual billing too, which is why the balances described in retention as working capital tend to grow on exactly the jobs with the most pending change work.

The revenue is another matter. It depends on whether a right to payment exists and can be enforced, which is a question about contracts rather than about whether the work was genuinely required. That distinction feels unfair on site, where the work was clearly instructed, and it is the distinction the accounting turns on.

Change OrdersRevenue RecognitionConstructionContractsClaims
01

Why unapproved work distorts the schedule

Under percentage of completion accounting, costs incurred drive the completion percentage. Costs on change work therefore increase percentage complete immediately.

If the associated revenue is not recognised, the job appears to have consumed more of its budget for the same contract value, which reduces estimated margin.

That is why unapproved change orders are one of the most common causes of large underbillings, as the work in progress schedule shows to any reader.

It also affects the estimate at completion, since the remaining budget now looks smaller than it is, which distorts the very number described in the estimate at completion.

A finance professional working through figures at a desk
The work happened. Whether it is revenue depends on the contract.
02

Four documentation levels

These sit on a spectrum, and the accounting consequence differs sharply along it.

Signed change order: Scope and price agreed in writing. Contract value increases and the accounting is straightforward.
Written instruction, price unresolved: The scope is documented and the amount is not, which raises a variable consideration question rather than an existence one.
Verbal instruction with contemporaneous notes: Site records, daily reports and correspondence, which is evidence and is weaker than agreement.
Verbal instruction, no record: The most common and the weakest position, and it is the reason the document you cannot find matters so much on site.
03

What determines whether revenue can be recognised

The question is whether an enforceable right to payment exists for the work performed, which depends on the contract terms and on the evidence of instruction.

Where the right exists but the amount is not agreed, the amount becomes an estimate subject to constraint, which means recognising an amount unlikely to reverse significantly.

Where the right itself is uncertain, recognition is generally not appropriate until it becomes probable, which is a different threshold from the amount question. Both assessments have to be revisited as negotiations proceed, so a position taken in month three is not a position for the life of the job.

Both assessments are fact specific and both benefit enormously from documentation created at the time rather than assembled during a claim.


Fairness is not the test. An enforceable right to payment is.
04

Three positions and what to do

Most pending change work sits in one of three states, and the finance response differs for each.

PositionAccounting questionAction
Approved and pricedNone. Contract value increases.Update the contract value and the schedule promptly rather than at month end.
Instructed, not pricedHow much can be recognised, subject to constraint.Record the scope, estimate the amount and document the basis.
Disputed or unrecordedWhether a right to payment exists at all.Assemble contemporaneous evidence now, and consider whether cost should be recognised without revenue.

Recognition of change orders and claims depends on the applicable framework, contract terms and enforceability. Confirm the treatment with your auditors and legal advisers.

"

The cost went into the job on Tuesday. The revenue depends on an email nobody kept.

ChatFin
05

The register that prevents most of this

One artefact does most of the work here, and it belongs with the project team rather than with finance.

Log every instruction the day it is given

Scope, who instructed it, date and estimated cost, regardless of whether paperwork follows.

Attach the contemporaneous evidence

Site reports, photographs, emails, gathered while they exist rather than during a claim eighteen months later.

Track status through to approval

Instructed, submitted, approved, priced, with an ageing report, because pending change orders age like receivables.

Report the value monthly

Pending change order value by job, alongside the schedule, which is what makes underbillings explainable, as in close metrics that change behaviour.

An accountant examining documents beside a calculator
Contemporaneous evidence is worth more than a well argued claim eighteen months later.
06

Two consequences of leaving it late

Both are commercial as well as accounting problems.

Consequence

Negotiating from memory

A claim assembled after the fact relies on reconstructed evidence, which weakens the negotiating position and usually reduces the settlement.

Consequence

Estimated margin looks wrong

The job carries costs without matching revenue, so margin appears to have deteriorated when in fact the revenue has not yet been recognised, which distorts every review that follows.

07

Where ChatFin helps

We work on the finance side of this: the visibility of pending change work and its effect on the reported position.

Pending value surfaced by job: Change order value at each status, drawn together with job costs so the effect on margin is visible rather than implied.
Ageing on pending approvals: Change orders sitting unapproved for extended periods raised as exceptions, since delay reduces recoverability.
Schedule impact prepared: The effect of pending items on percentage complete and margin prepared for review, alongside the rest of master data as the automation project.

Contract interpretation, claim strategy and the assessment of enforceability remain with your commercial and legal advisers.

Free tool

AI Cost Estimator for the CFO Office

Four inputs. A first year range, a timeline, and three delivery models compared. No login required.

Frequently Asked Questions

Can we recognise revenue on an unapproved change order?

It depends on whether an enforceable right to payment exists for the work performed and, if so, whether the amount can be estimated within the constraint on variable consideration. Both are fact specific assessments that turn on contract terms and evidence, so take them to your auditors.

What if the client accepts the work but not the price?

That is generally a variable consideration question rather than an existence question, since the right to payment is less doubtful than the amount. The recognised amount is constrained to what is unlikely to reverse significantly, and the basis should be documented.

How does this affect the WIP schedule?

Costs increase percentage complete immediately while revenue may not be recognised, producing underbillings and an apparent reduction in estimated margin. Reporting pending change order value alongside the schedule is what allows a reader to interpret the position correctly.

What documentation matters most?

Records created at the time: the instruction itself, daily reports, photographs and correspondence. Evidence assembled during a claim is materially weaker, both for the accounting assessment and for the commercial negotiation that usually follows.

Log it the day it happens

The cost is immediate. The right to payment has to be evidenced.

A change order register with status, value and contemporaneous evidence attached is the single artefact that keeps this from becoming a claim exercise.

If you want a first year range for change order tracking alongside job costing, the estimator gives one in about a minute.

Open the estimator
Book a Demo
Put it on your own numbers

See what this looks like in your ERP.

We will walk through the workflow behind this article on the system you already run, using your own data, and show what a first phase would actually cover.

✓Runs on the ERP you already have, on the version you already run
✓Every action prepared as a draft that a person approves before it posts
✓A first phase scoped against your real workflows, not a generic package
Schedule a Demo
Confidential & private

This article is general information for finance and accounting teams. It is not legal, tax, accounting or investment advice. Dates and thresholds are given as published at the time of writing and several of these timelines have moved before, so confirm the current position with your advisers and with the relevant authority before acting.